Prices as at 15 October 2026, checked weekly. Base location Abuja.

Bored cast-in-place pile 1200mm dia in C30/37 concrete incl. rebar cage and drilling fluid: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦682,733per m

Tender rate about ₦911,276 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for bored cast-in-place pile 1200mm dia in C30/37 concrete incl. rebar cage and drilling fluid is ₦682,733 per m in Abuja: ₦372,953 materials, ₦18,012 labour and ₦291,767 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦911,276 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialReady-mix C30/37, delivered Abuja (ex-pump)1.24 m³2%₦178,000₦225,134
MaterialHigh-yield rebar 12-16mm, per tonne0.11 tonne5%₦1,050,000₦121,275
MaterialBinding wire, per kg1.2 kg5%₦1,900₦2,394
MaterialBentonite (API grade), per tonne0.05 tonne5%₦460,000₦24,150
Plant (days)Bored piling rig (600-900mm)0.06667 day-₦3,449,850₦229,991
Plant (days)Mobile crane 25t0.06667 day-₦749,240₦49,950
Plant (days)Hydraulic excavator 20-22t (CAT 320/215 class)0.01429 day-₦827,850₦11,827
Labour (hours)Piling hand4 h-₦1,965₦7,860
Labour (hours)Iron bender / steel fixer3.2 h-₦2,456₦7,860
Labour (hours)Unskilled labourer2 h-₦1,146₦2,292
Materials₦372,953
Labour₦18,012
Plant₦291,767
Net unit rate per m₦682,733

Scope note: Rig mobilisation, testing and pile-head cut-off measured separately.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦682,733₦911,276
Lagos₦721,140₦962,539
Port Harcourt₦735,010₦981,053
Ibadan₦645,895₦862,106
Osogbo (Osun)₦654,559₦873,671
Kano₦637,535₦850,948
Kaduna₦641,805₦856,647
Enugu₦665,836₦888,723
Benin City₦675,762₦901,971
Uyo₦699,973₦934,287
Jos₦651,370₦869,414
Riverine / creek site₦913,128₦1,218,794

Related piling & ground engineering rates

Frequently asked questions

How much does bored cast-in-place pile 1200mm dia in C30/37 concrete incl. rebar cage and drilling fluid cost per m in Nigeria?

About ₦682,733 per m net in Abuja as at 15 October 2026, or about ₦911,276 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦721,140 per m and the tender rate about ₦962,539 per m.

What does the rate include?

Materials (Bentonite (API grade), Binding wire, High-yield rebar 12-16mm, Ready-mix C30/37) with waste allowances; labour (Iron bender / steel fixer, Piling hand, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Bored piling rig (600-900mm), Hydraulic excavator 20-22t (CAT 320/215 class), Mobile crane 25t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Rig mobilisation, testing and pile-head cut-off measured separately.