Temporary sheet piling PU18 driven and extracted (30% material write-off/hire): cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦86,008per m²

Tender rate about ₦114,799 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for temporary sheet piling PU18 driven and extracted (30% material write-off/hire) is ₦86,008 per m² in Abuja: ₦62,740 materials, ₦1,376 labour and ₦21,893 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦114,799 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialSheet pile PU18 (128 kg/m2 of wall), per m20.3 m²3%₦203,043₦62,740
Plant (days)Vibratory hammer with crawler crane (sheet piles)0.01111 day-₦1,970,350₦21,893
Labour (hours)Piling hand0.7 h-₦1,965₦1,376
Materials₦62,740
Labour₦1,376
Plant₦21,893
Net unit rate per m²₦86,008

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦86,008₦114,799
Lagos₦90,977₦121,432
Port Harcourt₦92,710₦123,744
Ibadan₦81,501₦108,784
Osogbo (Osun)₦82,498₦110,114
Kano₦80,178₦107,017
Kaduna₦80,847₦107,910
Enugu₦84,040₦112,173
Benin City₦85,133₦113,631
Uyo₦88,341₦117,913
Jos₦81,912₦109,332
Riverine / creek site₦113,725₦151,794

Related piling & ground engineering rates

Frequently asked questions

How much does temporary sheet piling PU18 driven and extracted (30% material write-off/hire) cost per m² in Nigeria?

About ₦86,008 per m² net in Abuja as at 15 October 2026, or about ₦114,799 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦90,977 per m² and the tender rate about ₦121,432 per m².

What does the rate include?

Materials (Sheet pile PU18 (128 kg/m2 of wall)) with waste allowances; labour (Piling hand) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Vibratory hammer with crawler crane (sheet piles)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.