Geosynthetic clay liner laid with overlaps: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦9,976per m²

Tender rate about ₦13,316 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for geosynthetic clay liner laid with overlaps is ₦9,976 per m² in Abuja: ₦9,919 materials, ₦57.31 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦13,316 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialGeosynthetic clay liner (GCL), per m21.15 m²15%₦7,500₦9,919
Labour (hours)Unskilled labourer0.05 h-₦1,146₦57.31
Materials₦9,919
Labour₦57.31
Plant₦0
Net unit rate per m²₦9,976

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦9,976₦13,316
Lagos₦10,576₦14,116
Port Harcourt₦10,767₦14,371
Ibadan₦9,469₦12,638
Osogbo (Osun)₦9,565₦12,767
Kano₦9,267₦12,370
Kaduna₦9,368₦12,504
Enugu₦9,766₦13,035
Benin City₦9,867₦13,169
Uyo₦10,265₦13,701
Jos₦9,468₦12,637
Riverine / creek site₦12,957₦17,295

Related piling & ground engineering rates

Frequently asked questions

How much does geosynthetic clay liner laid with overlaps cost per m² in Nigeria?

About ₦9,976 per m² net in Abuja as at 15 October 2026, or about ₦13,316 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦10,576 per m² and the tender rate about ₦14,116 per m².

What does the rate include?

Materials (Geosynthetic clay liner (GCL)) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/p17-geosynthetic-clay-liner-laid-with-overlaps/, prices as at 15 October 2026.