Settlement plate installed and initial reading: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦103,668per unit

Tender rate about ₦138,370 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for settlement plate installed and initial reading is ₦103,668 per unit in Abuja: ₦85,000 materials, ₦18,668 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦138,370 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialSettlement plate with riser pipe1 unit-₦85,000₦85,000
Labour (hours)Geotechnical technician4 h-₦4,094₦16,375
Labour (hours)Unskilled labourer2 h-₦1,146₦2,292
Materials₦85,000
Labour₦18,668
Plant₦0
Net unit rate per unit₦103,668

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦103,668₦138,370
Lagos₦110,261₦147,170
Port Harcourt₦109,534₦146,200
Ibadan₦95,684₦127,714
Osogbo (Osun)₦95,601₦127,603
Kano₦93,051₦124,199
Kaduna₦94,461₦126,081
Enugu₦98,234₦131,118
Benin City₦99,457₦132,750
Uyo₦103,417₦138,036
Jos₦95,311₦127,216
Riverine / creek site₦131,034₦174,898

Related piling & ground engineering rates

Frequently asked questions

How much does settlement plate installed and initial reading cost per unit in Nigeria?

About ₦103,668 per unit net in Abuja as at 15 October 2026, or about ₦138,370 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦110,261 per unit and the tender rate about ₦147,170 per unit.

What does the rate include?

Materials (Settlement plate with riser pipe) with waste allowances; labour (Geotechnical technician, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.