BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Ground/rock anchor 32mm bar, drilled and grouted: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦42,294per m

Tender rate about ₦56,451 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for ground/rock anchor 32mm bar, drilled and grouted is ₦42,294 per m in Abuja: ₦13,043 materials, ₦1,572 labour and ₦27,679 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦56,451 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialGround anchor bar 32mm high-yield, per m (incl. couplers)1.05 m5%₦9,028₦9,953
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.25 bag3%₦12,000₦3,090
Plant (days)Micropile / anchor drilling rig0.03333 day-₦694,080₦23,136
Plant (days)Grout mixer & pump0.025 day-₦181,710₦4,543
Labour (hours)Piling hand0.8 h-₦1,965₦1,572
Materials₦13,043
Labour₦1,572
Plant₦27,679
Net unit rate per m₦42,294

Scope note: Stressing and head excluded.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦42,294₦56,451
Lagos₦44,586₦59,511
Port Harcourt₦45,473₦60,695
Ibadan₦39,943₦53,314
Osogbo (Osun)₦40,548₦54,122
Kano₦39,604₦52,861
Kaduna₦39,781₦53,098
Enugu₦41,165₦54,944
Benin City₦41,880₦55,899
Uyo₦43,279₦57,767
Jos₦40,465₦54,011
Riverine / creek site₦57,435₦76,661

Related piling & ground engineering rates

Frequently asked questions

How much does ground/rock anchor 32mm bar, drilled and grouted cost per m in Nigeria?

About ₦42,294 per m net in Abuja as at 15 October 2026, or about ₦56,451 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦44,586 per m and the tender rate about ₦59,511 per m.

What does the rate include?

Materials (Ground anchor bar 32mm high-yield, OPC 42.5 cement) with waste allowances; labour (Piling hand) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Grout mixer & pump, Micropile / anchor drilling rig) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Stressing and head excluded.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/p16-ground-rock-anchor-32mm-bar-drilled-and-grouted/, prices as at 15 October 2026.